Level: Introductory
Kurt
Bittner, Communities of Practice Architect, IBM
25 Mar 2004 Updated 14 Mar 2006
Deriving from a RUC 2003 presentation, this article
explores how to plan a project based on the IBM Rational Unified
Process (RUP) using a use-case based approach. Patterns for
planning iteration in each phase are presented, providing you with
a simple and practical approach to organizing the project
work.
A Brief Overview of Iterative
Software Development
Everyone struggles with how to find and write use cases, develop
them, detail them, and so on. Once you have mastered these skills,
the next questions are:
- When do I do it?
- In terms of the Rational Unified Process® (RUP®) phases --
Inception, Elaboration, Construction, and Transition -- when do
things happen?
- Do I do work on use case A in iteration one, and use
case B in iteration 2 (and so on)?
This article provides some background on iterative development in
general, and then discusses how to drive the iterations with use
cases and how to work on parts of use cases in different iterations.
We'll also talk about what to do in the various RUP phases (such as
which tasks you should complete in Inception, in Elaboration, and so
forth).
Before we get to that, let's make sure that we understand RUP's
phases, as well as the concept of how iterations are grouped into
phases. RUP's phases, especially, tend to be misunderstood: people
mistakenly equate Inception with Requirements, Elaboration with
Analysis and Design, Construction with Implementation, and
Transition with Deployment. The latter is almost true, but the other
statements could not be more false. First, however, let's discuss
planning the overall project lifecycle.
Planning the Overall
Project
In a project following a "Waterfall" process lifecycle, the
typical approach is as follows:
- Capture all the requirements
- Analyze those requirements
- Define the design
- Code the components of the solution
- Integrate the components
- Test the integrated solution.
There can be feedback loops between these steps, but the dominant
practice is that a particular discipline is mostly completed before
moving on to the next discipline. In contrast, using an iterative
process you accomplish a small amount of each of the RUP
disciplines (requirements, analysis, design, implementation, and
testing) in every iteration. However, when you try to
implement this process, you may run into immediate difficulties in
the Inception Phase, as it is often unclear what (or how much) to
do, when to do it, and how to drive the process with use cases. A
better understanding of the RUP phases will mitigate this
challenge.
|
| Figure 1: Conventional (Waterfall) versus Iterative
software development |
One of the most positive aspects of the Iterative development
process, on the other hand, is that it addresses the problem of not
knowing where you really are until you start trying to integrate the
parts (fairly far into the project), only to find out that things do
not fit together quite as well as you thought they would. An
iterative approach addresses certain kinds of risks sooner by
implementing and integrating risky components earlier in the
process. The reason this reduces risk is that you can really only
know whether you have mitigated a risk after you have actually tried
to build something and put the pieces together. Figure 2 illustrates
some important differences in the two approaches.
|
| Figure 2: Lifecycle characteristics
|
The way that we confront risk using an iterative approach with
use cases is first to identify our risks, and then use those risks
to create use case scenarios that will force us to confront those
risks. We should then analyze, design, implement, and test one or
more of these scenarios in any given iteration. To avoid having to
implement large amounts of the system too early, you might determine
which parts of the system are architecturally insignificant or less
time -- sensitive, and then stub1
in those parts in the early iterations. In this way, you avoid
spending time building parts of the system that don't help you
reduce risk. The net effect of this approach is that-by implementing
the risky parts of the system first -- we have objective measures of
progress in mitigating risks very early in the project.
The RUP
Phases
The RUP divides the project into four phases, each of which is
focused on a specific set of risks. Figure 3 presents a summary of
the phases.
|
| Figure 3: The focus of RUP phases
|
Activities in each phase focus primarily on reducing risks and
moving the project ahead. Each phase conclusion represents a
milestone, a point at which you should evaluate results and
re-evaluate the decision to move ahead with the project. Figure 4
shows a summary of the milestones and their relationship to
phases.
|
| Figure 4: Major milestones |
In the following sections, we will briefly describe the focus of
-- and activities performed in-each phase.
The Inception
Phase
The purpose of the Inception phase is to bring business risks
under control. What we mean by this is that we want to make sure
that we:
- Understand the problem that we're solving
- Have confidence that we have an economically and technically
viable approach for delivering a solution
To describe the problem's solution, we need a way to express what
the system will do -- we typically do this by identifying (and
briefly explaining, but not detailing) the use cases the
system will have to support. Furthermore, to assess the technical
viability of the system, we need to explore and quantify enough of
the solution to understand whether it is possible, and how much it
will cost (time and money). Only then can we discern whether the
project is worth doing.
By the end of Inception we will be reasonably certain that the
project is viable -- we know that:
- We can build the system
- It solves the intended problem
- We can do it within the target date and budget of the
organization
We still don't know details about what we need to do or how we
are going to do it, but we do know that our project is feasible.
The Elaboration
Phase
The purpose of the Elaboration phase is to bring the
architectural and technical risks under control by:
- Taking a deeper look at the solution we proposed in the
Inception phase
- Examining whether it really is feasible
The basic approach we take is to build the complex, technically
novel, or risky parts of the solution. We do this to make sure that
we are not being overly optimistic in our belief that the solution
will work. The emphasis here is on actually building and testing
parts of the system, not just reviewing designs and plans. By
the end of the Elaboration phase we will have had to confront issues
such as:
- Performance
- Scalability
- Reliability
- Other technical issues
In this way we ensure that our proposed solution will actually
work.
Even if we believe that we already have a proven architectural
approach -- either because our solution has been used to solve
similar problems, or because we are building the solution using
middleware that has pre-defined architecture -- the Elaboration
phase still plays an important role. In this situation we would want
to evaluate whether the proposed (or candidate) architecture
can mitigate the technical risks that we have identified. Until
we can prove that the chosen approach is technically viable, we are
still in the Elaboration phase (regardless of what the schedule
says).
The Construction
Phase
In Construction, we bring the logistical risks of the project
under control. We have a large amount of work to get done, but
if the business and technical risks are controlled, then it's just a
question of being able to do all the work:
- In the time allotted
- Within the budget
- With the resources allocated
You might need to do some scope management, but in general the
focus of Construction should be cranking the work out. You can
manage a large-scale project by using teams working in parallel,
with integrated builds, branching, and merging changes using a
change management system. At the end of Construction, you have a
usable solution, but it is not yet fully deployed to its users.
The Transition
Phase
The purpose of Transition is to roll the solution out into its
target user community. In Transition you must:
- Train the users
- Establish back up and recovery policies
- Instantiate the solution at a data center
- Convert data, and so on
In other words, we need to take care of all the practical,
essential activities that need to occur before a solution can be
implemented.
The Distribution of Work
Across Phases
|
| Figure 5: Distribution of work across phases
|
As mentioned previously, a common misconception is that the
Inception phase is mostly concerned with Requirements, the
Elaboration Phase with Design, the Construction phase with
Implementation, and the Transition phase with Deployment. Figure 5
depicts the fact that each of the disciplines plays a role in each
of the phases. For example, while we perform 40% or 50% of the
requirements work in the Inception Phase, we also do some design and
implementation, some deployment, and some management overhead
(planning, estimating and measuring). The focus of the design and
implementation work in Inception is on proof-of-concept prototypes
that explore the business viability of proposed solutions.
In Elaboration (the next Engineering Phase), we conclude perhaps
60 -- 70% of the requirements work, half the design, and half the
overall management effort. By Construction, requirements should be
mostly complete -- you're getting ready to roll out the solution in
the form of a beta release -- but there may be a few lingering
issues. By the time you finish the Transition Phase, the work is
complete.
Each phase concludes with a major milestone
that corresponds to certain kinds of risk being mitigated.
Each iteration concludes with a minor milestone
(see Figure 6) at which we assess the results achieved in that
iteration. The iteration assessment may result in us identifying new
work, so we need to take this into account when creating a plan for
subsequent iterations.
|
| Figure 6: Phases and iterations
|
The phase and iteration milestones act as evaluation points we
can use to make sure that we're on track, allowing the project to
adjust to change and adapt to new information.
|
| Figure 7: What is an iteration?
|
In each iteration, we take some set of scenarios and go through
each of the RUP disciplines: Requirements, Analysis & Design,
Implementation, and Test (illustrated in Figure 7). As an example,
consider what deployment means in an Inception phase. We might do a
proof-of-concept prototype, show it to some people, and ask if it is
what they want. This doesn't mean that we are writing
production-quality code in this iteration of the Inception phase,
and it does not mean that we are doing exhaustive release testing,
but it does mean that we do some implementation and testing in
addition to all of the other work that we need to do. As we progress
through the Elaboration phase and into the Construction phase, we
are increasingly creating code that will survive in the final
product.
|
| Figure 8: Use cases drive development
|
How do use cases figure into this? Figure 8 shows a simple model
of how use cases drive the behavior of the system. The relative size
of the description shown in the box labeled "Use Cases" represents
the fact that generating a description is most of the work involved
in creating a use case. The little white box around some of the text
in this document symbolizes a scenario. A scenario is a subset of a
use case -- specifically, the basic flow plus zero or more alternate
flows.
On the upper right we see a sequence diagram. This part of the
figure is intended to show that each scenario has an associated
collaboration that "fulfills" or "realizes" the scenario. Components
participating in these collaborations interact with each other to
realize or to provide the behavior specified by the use case. On the
lower right we see that associated with each use case realization
there are test cases that test either the scenario (white-box tests
based on the use-case realization) or the use case itself (black-box
tests based on the use-case description). Elsewhere in the figure we
see that documentation and UI design, among other things, can be
derived from use cases.
That's a brief overview of iterative development and its major
concepts. It's important to understand these concepts in order to
understand the details of how we can successfully complete the
actual project work.
Planning
Projects
|
| Figure 9: Plan levels |
Planning occurs at multiple levels. At the highest level is the
Program Plan. A program coordinates multiple projects. To
understand when a program would be useful, consider building a new
kind of ATM that can dispense cash, provide theater tickets, and
allow users to pay their parking tickets. If we were going to deploy
this product across a nationwide (or perhaps worldwide) banking
network, we would have to accomplish many high-level tasks:
- Coordinate work across many different systems and locales
- Change the software currently running in the financial
institutions
- Coordinate that change with the rollout of the ATM software
and hardware
- Coordinate all of the system changes with a marketing program
that will educate consumers about the new product offering
The coordination of work across all the projects needed to do the
work would require a program. To keep things simple for the rest of
our discussion, we will focus on a single project.
The Project Plan is an achievement-oriented plan for the
overall project that:
- Defines the dates of the major milestones (phase ends) of the
project
- Maps risks to the phases in which they will be addressed
- Maps scenarios to the phases in which they will be addressed
- Provides a high-level overview of the resources needed in each
phase (this will be refined in each of the phase plans)
The overall project plan delegates the details to the lower level
plans -- phase and iteration plans. Often, it is very natural to
combine the project plan and the phase plans.
In addition to the Project Plan, there is a detailed plan for
each iteration describing the work that we will do in that
iteration. An Iteration Plan identifies:
- The scenarios on which to focus
- The nonfunctional requirements to handle
- The test cases we will execute to validate the
scenarios
To create the iteration plan, we consider the risks that are
mapped onto the iteration, and then select scenarios and
supplementary (typically non-functional) requirements that will
force confrontation of those risks. From this starting point, we map
out a series of activities to take these scenarios and supplementary
requirements through the RUP disciplines discussed previously
(requirements, analysis, design, implementation, test, and
deployment).
Figure 9 shows the relationship between plans, moving from a
high-level plan (of a program consisting of multiple projects) to
project plans, to phase plans, and then to iteration plans.
Planning, Estimation and
Risk
Most project management approaches consider risk and create a
risk list. The difference between these conventional approaches and
an iterative approach is the degree to which the risk list drives
the overall project work. In the RUP, the risk list is the main
driver of the planning effort, second only to the overall project
objective. Aggressively confronting risk is the central theme of
planning in the RUP. Risk reduction drives everything, including
decisions about how we use (or even if we should use) use cases, as
well as how much detail we should put in the use case
descriptions.
|
| Figure 10: Estimate accuracy increases as the
project progresses2
|
Many people try to develop a detailed project plan at the
beginning of the project, and then try to manage the project to this
detailed plan. Using this approach, most projects end up over budget
or late -- mostly not because the work was bad, but because the
original plan and budget were bad. Figure 10 shows the variability
in estimates over the course of the project. Most initial project
plans are little more than conjectures, because there is little
information on which to base estimates -- at the start of things, we
don't know very much, and what you think you know may be wrong. As
we get deeper into the project we get more information, which
reduces the variability of the estimates. In addition, there is less
work to estimate, and that further reduces errors.
We can use various approaches to develop estimates, and in fact
different estimation models are useful at different points in the
project. At the very beginning of the project (when there is little
more than a notion that there is a problem and a sketchy vision for
one or more solutions), all we may be able to do is to base
estimates on hunches, which in turn are based on comparisons to
similar projects. A little later in the Inception phase and into the
early Elaboration phase (when we have a little more information
about the requirements for the solution), techniques like function
point analysis -- or its close cousin use-case point analysis -- can
give you a better idea of the overall effort. By the time we are
well into Elaboration, we have the emerging architecture to work
with, and we can use more sophisticated estimation models such as
CoCoMo II3
as the basis for our estimates. The Transition phase is driven by a
completely different set of factors -- things like the number of
sites and the number of users to which the solution will be
deployed. As we go through each iteration, we periodically revise
our estimates to ensure that our expectations are still
realistic.
A Pattern for Organizing
Work in an Iteration
As introduced previously in Figure
7, the general pattern of iteration is to more completely
describe the requirements related to the risks assigned to the
iteration, then analyze, design, implement, and test the part of the
system needed to support the scenarios associated with the
iteration's risks. Figure 7 implies a rather strict sequence of
activities, but the reality is far more flexible. In addition, a
great deal more happens in parallel.
Many project management approaches specify a standard work
breakdown structure, and in the pattern for work performed in an
iteration described above we can see the basic building blocks for
planning an iteration. In a simplified way, the work of an iteration
can be viewed as shown in Figure 11.
|
| Figure 11: Discipline-specific work occurs largely
in parallel in an iteration |
Measuring Phase and
Iteration results
At the end of each iteration, we need to take stock of what we
have achieved:
- Have we mitigated the risks we set out to address?
- Have we implemented the parts of the solution needed to
support the scenarios we selected for the iteration?
- If we didn't accomplish as much as we thought we would, how
will we adjust our plans for future iterations?
- Can we still get all the work done, or do we need to consider
reducing the project scope?
In evaluating results and adapting our plans for the future, we
need to take care not to ignore signs that we are falling behind.
When we don't succeed in mitigating a risk, it's easy to keep
putting it off and saying that we will catch-up later -- but of
course when we do this we take the first step toward serious
trouble. When we don't achieve intended results in an iteration, we
need to take a serious look at the scope of the project, and at the
very least rethink our plans for future iterations.
Even more serious trouble starts when we don't achieve our
targets for a phase, but keep moving ahead anyway. Phases are
achievement-based -- you should never move on from one until you
have mitigated the risks associated with that phase, regardless of
what your schedule says. This is where we most often come into
trouble -- by ignoring the warning signs, we set ourselves up for
future failure. We will discuss this more later.
Planning and Managing the
Inception Phase
Some people struggle with the purpose of the Inception phase. Our
earlier statement that the Inception phase is focused on mitigating
"business" risks seems confusing because the development team
assumes that the business stakeholders are handling the business
decisions and risks4.
We have found that even when it appears that someone else is looking
after the business issues, having the developers invest in learning
about the business goals and risks results in the definition of
better solutions. The common case is that there are a lot of issues
that fall right between business and technical issues --
availability, security, performance, throughput, and so on. In this
case, an awareness of both sides of an issue leads to better
results. The Inception phase provides a framework for
collaboratively working through these issues from both the business
and technical perspectives.
The overall project plan establishes the basic timetable for the
phase, and identifies specific risks that will be handled in the
phase. Since the Inception phase focuses on mitigating business
risks, the Inception phase focuses on ensuring that the rest of the
project, if funded, will result in something valuable to the
organization. This usually means that the project will create a
positive return on investment, satisfy a mandatory (perhaps
legislated) requirement, or meet some time-to-market requirement. In
the Inception phase, we identify problems and their root causes, and
then develop a vision for their solution.
The work in the Inception phase tends to organize into tracks
based on three kinds of activities:
- The Problem Track: Activities related to understanding the
problem
- The Solution Track: Activities related to identifying
potential solutions
- The Project Track: Activities related to organizing the
project that will build the solution
These tracks work largely in parallel and interact with each
other -- the problems to be solved affect the range of potential
solutions, which in turn affects the way the project organized to
deliver the solution is run. In turn, the way the project is
organized and funded often constrains the solution that we can
build, and so on.
The Problem Track
In the Problem track we try to get at the root causes of
problems. For instance, the starting point of most projects is when
symptoms of some problem present themselves -- costs are too high,
customers are not satisfied, customer needs are unmet. We need to
understand what the real problems are before we can propose
solutions. A variety of techniques can be applied, most of which
center around continually asking, "Why is that?" when we find a
problem. When we get to the point where there are no more "whys", we
are ready to find the right solution.
To understand the problem more fully, we usually need to know who
experiences it. By considering who is affected by the problem, we
come to better understand the problem -- and the aspects of it --
that need to be solved. To do this effectively, we should interview
stakeholder representatives to understand how they are affected by
the problem, and what they would like to see in the solution.
In addition, we need to be aware of the benefits of solving the
problems identified, so that we can evaluate the cost-benefit of
various solutions. The benefit of solving the problem is of course
independent of the cost of the potential solutions. Nevertheless,
knowing the value of solving the problem can help us to establish a
ceiling on how much we would be willing to spend to solve it. This
helps us eliminate some potential solutions early in the
identification process, before we spend a lot of time describing the
potential solution.
One potential trap in the Problem track is to"problemify" a
solution (as one client with whom we have worked put it). In other
words, someone on the team already has a solution in mind and merely
rephrases it as a problem. We need to make sure that we understand
the real problems, not just reinforce our preconceptions of a
solution. This is more difficult than it may first appear -- it is
very easy to jump to conclusions about the problem. At the same
time, we cannot become paralyzed by endless problem analysis.
The Solution track
In the Solution track we explore alternative solutions to the
problems identified in the problem track. Projects usually fail here
by not being creative enough -- not exploring enough alternative
solutions, focusing on defining the details of a single solution too
early. We can use various brainstorming techniques to identify a
number of potential solutions to each problem identified. The focus
should first be on identifying (without judgment) potential
solutions, excluding only solutions that are obviously too expensive
given the value of solving the problem.
In identifying solutions, we should make sure that the solution
will help each of the types of users affected by the problem. The
people affected by the problem become one set of stakeholders to the
solution. Other stakeholders include people who are affected by the
solution (people who will support the solution but might not use the
solution), and the project team itself.
Use cases can help us to define potential solutions by helping us
to describe what they will do for the stakeholders. They help us to
explore and define the behavior of the solution. It's important to
recognize that a use-case model describes a potential
solution. As a result, it may be useful to develop several separate
use-case models to compare alternative solutions. These models can
help us to visualize different solutions and get feedback from
stakeholders on different proposals, all of which can help us decide
whether to move ahead with one of the alternatives.
When developing these use-case models we at a minimum identify
the primary actors and briefly describe and outline the alternative
flows. We will need this much information to define the scenarios
and develop a rough estimate of the solution's overall schedule and
cost. Then we can decide whether or not to proceed with the
solution. As we describe the solution using use cases, we need to
walk through the model with key stakeholders in order to confirm
that we correctly understand the problem, and to evaluate if this
potential solution would meet the stakeholders' needs. Their
feedback mitigates the risk of spending lots and lots of money
developing something that nobody wants and that doesn't solve the
real problem. Sadly, this happens more times than we would like to
admit.
In addition to the use-case models, small functional prototypes
are often useful to gather feedback on potential solutions. For
instance, we might walk the stakeholders through a set of scenarios
using screen mock-ups to get feedback on proposed solutions. The
important thing is to keep the investment low and flexibility (being
able to revise the solution approach) high while our idea of what we
are going to build is still evolving.
The Vision document presents a summary of a particular solution
and the perceived problems that it solves. If we have several
credible potential solutions, then we should develop separate Vision
documents for each one. Separate vision documents are valuable if we
want to make a formal choice between alternative approaches.
Typically, though, most projects settle on a single approach after
an informal exploration of alternatives.
The Project Track
The development team performs a third set of activities in the
Inception phase -- those related to planning and initiating the
project itself. While the Solution track activities identify and
define potential solutions, the function of the Project track is to
estimate the cost, resources, and a high-level schedule for the
project, to determine whether the proposed solution is economically
viable.
The fact that we lack defined solutions at the start of Inception
creates a dilemma: at the start of the this phase (and therefore the
product), we really don't have a clue about how long the project
will take and how much it will cost. This is the fatal flaw of the
"plan at the beginning" crowd who want to devise a very detailed
plan early on and then execute to the plan for the rest of the
project5.
We have to accept a fair degree of uncertainty in the Inception
phase in order to move ahead.
Once we do select a potential solution, however, our work
on the Project track creates a plan for the rest of the project:
- Define the duration and goals of each phase
- Plan the iteration structure of each phase
- Map preliminary risks and scenarios onto iterations
- Create a resource plan for the project
- Identify the skills and staffing levels that will be required
for the phases
- Develop an overall project estimate
Occasionally, a question arises regarding whether we need
multiple iterations in the Inception phase: the answer is,
"sometimes". In the following cases, it may take more than one
iteration to determine whether a particular solution is really the
right one:
- The business problems are difficult to diagnose
- The suitability of a solution is hard to understand
- The solution is technically unproven
- It is hard to choose between multiple solutions
It is usually impossible to predict this at the very start of the
Inception phase, so the decision is usually made after completing
the first iteration. At this point, we can decide whether or not we
need more time to assess the viability of one or more proposed
solutions before proceeding to the Elaboration phase.
The Inception Phase for the ACME Super ATM
Going back to the example, if we're going to build this new
super-duper ATM (Figure 12) -- Java-based, more modular and with a
lower cost of development, more configurable so we can do all kinds
of different dispensers (postage, event tickets, pay parking tickets
and so on)-- then we need a framework for planning the project.
Since as we discussed earlier the purpose of the Inception phase
is to bring business risks under control, we should assess the
market need. Perhaps we can define this need as giving people
flexible access to their funds and enabling them to use these funds
in a number of different ways. We are building this ATM for
financial institutions, so we have identified a target
market. To complete our work in the Problem track, we will need
to gather a set of stakeholders from those institutions to
understand their needs. We will also need to have customers
represented by other stakeholders who we will work with to make sure
that we understand the problems that they would like our potential
solution to solve.
|
| Figure 12: The ACME Super ATM |
In the Solution track we take this problem description
information and formulate ideas about how we will solve it. In fact,
we have jumped ahead a little bit because we appear to have started
out with a solution in mind (a new kind of ATM), but in practice
this is rather typical. Since we do have a solution in mind, we will
need to figure out whether there is actually a need for this in the
market. One way to do this is by comparing the problems experienced
by stakeholders with existing solutions on the market. If we find
that there is no competition, our task will be easier. If other
competitors have partial solutions to the problem, then we need to
understand how our solution could be different. We capture all this
analysis in the Vision document for the solution.
One of the risks of building this new ATM is that the market is
crowded. Who wants to buy this? If it doesn't significantly differ
from existing products on the market, then why do it?
Our potential solutions will encompass various "what if"
scenarios. For example:
- If we cannot price the product aggressively, maybe we can
build a super-duper ATM.
- If it turns out that our new fancy ATM is four times more
expensive than the existing ones on the market, and the financial
institutions make a fraction of a cent per transaction dollar,
maybe we will have a great solution that no one wants to
buy.
We will have to assess our total cost of development, divide it
by the number of units we expect to ship, and compute the
development cost per unit. We then need to decide how much margin we
will need to cover all the other things we need to do to sustain the
product -- technical support, marketing, and related overhead.
In addition to cost and pricing information, we need to assess
the real market need -- do customers really want the kind of
services offered by the ACME Super ATM? Will people use an ATM to
pay bills, get theater tickets, and perform non-traditional ATM
services? After all, when ATMs were first introduced, it took many
years before the public readily accepted them.
To try to answer these questions, we need to build a small
prototype of the potential solution. For instance, we could mock-up
our new ATM and subject it to test marketing, or we could build an
ATM with limited functionality and take it to a usability lab,
bringing people in to see if they would want to use its services.
Think how much money the "new economy" firms of a few years ago
could have saved had they done this kind of analysis before spending
millions perfecting business models around services that people did
not want to purchase.
Building this prototype also has an additional benefit -- it
helps us to understand the potential costs of the solution. As noted
previously, this information feeds back into the estimates needed to
evaluate the financial worthiness of the solution.
Concluding the Inception Phase
To conclude the Inception phase, we need to do a few more things.
First, we need to settle on a single solution proposal that we are
going to take forward. To do this, we need to make sure that the
solution:
- Solves the right problem
- Is (as far as we can tell at the moment) technically feasible
- Is economically viable
We need all stakeholders to agree on these three points, at least
insofar as they are willing to take the project to the next step,
assessing the technical viability and developing the "architecture"
of the approach.
Second, we need to create the plans for the project, laying out
the phases, describing major milestones, and mapping risks and
scenarios to iterations. We need to do this to assess the economic
viability of the project, but we also need to do this to move the
project ahead.
Finally, we need to start gathering the team for the rest of the
project. If the project is to go forward, we are going to need
people with specific skills to fill out the resource plan, and it
might take a while to find the right people.
It should be said at this point that a completely acceptable, and
perhaps even desirable, outcome of the Inception phase is a decision
not to go ahead with the project. Some problems are not
solvable given the investment that the organization can afford to
make, and other problems cannot be solved at all. It is sometimes
better to decide to focus on solving other problems than to waste
time solving a problem whose solution is uncertain or expensive.
Canceling a project at the end of Inception is often the best
solution; it is a much bigger (and more expensive) mistake to let a
project continue when there is little hope for real success.
Planning and Managing the
Elaboration Phase
At the conclusion of the Inception phase we have achieved a
couple of important things: we have agreement on:
- The problems being solved
- A tentative solution to those problems
- How much that solution will cost
As we move into the Elaboration phase we turn our attention to
assessing the technical details of the solution, ensuring that the
solution is really technically feasible, and making important and
irrevocable6
technical decisions about the solution. To do this we have to come
to a more detailed understanding of the requirements, and we have to
build and test critical parts of the solution to make sure our
assumptions are correct.
As we have discussed already, the basic pattern of iteration
planning is to choose a set of scenarios (along with related
supplementary requirements) using a set of risks that we need to
address in that iteration (as defined by the Project plan). The
risks addressed in the Elaboration phase are technical risks,
or risks related to technical aspects of the solution. Often, these
technical aspects relate to various system qualities such as
performance, reliability, scalability, security, portability, and so
on. We say that the Elaboration phase focuses on architectural
issues because solving these "architectural" challenges requires a
consistent, systematic series of decisions and actions that has a
pervasive effect on the solution. Changing these decisions later,
after the development of the system is well under way, is typically
prohibitively costly in terms of both schedule and budget.
The Elaboration Phase and the Art of Scenario
Selection
Planning the Elaboration phase is an art that requires a certain
amount of intuition about the kind of technical challenges
that the team will encounter when forced to analyze, design,
develop, and test a particular scenario. A scenario consists of the
basic flow of a use case plus zero or more alternative flows. The
architecturally significant scenarios are those which are
going to strain the solution to its limits. Intuition comes into
play at the point when planning needs to be done, because at that
time you have very little in the way of definition to work with --
the scenarios may be loosely identified, but the use case and their
flows (on which the scenarios are based) have not yet been fully
described. Furthermore, since we don't yet know the details of the
use cases we certainly can't know how the system will realize those
use cases.
The art of choosing the right architecturally significant
scenarios lies in being able to visualize and anticipate that a
particular scenario will entail a particularly difficult technical
problem. This anticipation is honed by experience with similar
problems, and requires insight into a variety of different
problem-solving approaches. The skills required are often those of
both generalist and specialist -- the ability to broadly understand
a large variety of approaches combined with the ability to reason
deeply about specific approaches.
In selecting scenarios for the Elaboration phase, we have to
strike a balance between:
- The number of scenarios
- The degree to which they force us to consider technical risks
- The amount of time and resources we have available
If we selected all scenarios we would cover most of the technical
risks, but we would also take up all available time on the project.
If we select only a few scenarios, we risk missing some significant
issue. The art of scenario selection also lies in being able to
address the greatest number of risks with the fewest number of
scenarios necessary to minimize the risk that we may miss
something.
One set of scenarios that are important to consider but easy to
forget are those related to installation, configuration, and
maintenance of the solution. Today, these issues represent some of
the more complex aspects of many solutions, because there is never a
good time to shut down a 24 by 7 system for maintenance. As a result
we may need to incorporate capabilities that allow us to make
changes or upgrades without having to shut the system down. These
capabilities require great forethought, planning, and creativity,
and we should handle these issues now in the Elaboration phase.
The best way to achieve this balance is to have an experienced
solution architect. By experienced, we mean someone with the
required breadth to understand the potential for alternative
approaches and the depth to understand the risks inherent in those
approaches. Finding the right person for this role is often the
project manager's most important task in the early days of the
project.
The number of iterations needed in the Elaboration phase will
depend on several factors:
- The total number of architecturally significant scenarios
- The number of scenarios that can be worked simultaneously
- The dependencies between issues that you will address as the
scenarios are worked
The team in the Elaboration phase is still likely to be rather
small to keep communication overhead low, so it may take several
iterations to prove the viability of the solution.
Assessing Technical Feasibility and Architectural
Stability
The important idea about architecting is that we need to build
and test parts of the system in order to be sure that we have
an acceptable solution. As with scientific experiments, a proposed
solution is a kind of theory that we need to prove or disprove. Like
scientists, we need to conduct experiments to see whether our theory
about the solution's suitability is correct. We perform these
experiments by building part of the system and conducting tests. We
don't need to build the whole system to conduct these tests; we can
build just enough to test our hypothesis about the suitability of
some aspect of our solution. Another way of thinking about the
Elaboration phase is that it is for R&D, as opposed to the
Construction phase, which is more like manufacturing.
More often than not, assessing the technical feasibility of a
proposed solution means assessing its performance and scalability.
It may seem that we have to build quite a lot of a solution in order
to evaluate its suitability, but the reality is that in many systems
the number of parts that are affected by scalability concerns is
rather small. As a result, our challenge becomes selecting the parts
of the system that will be affected by various technical challenges
(architectural risks), building them into an architectural
prototype, and them subjecting them to simulated real-world
workloads.
The Elaboration Phase for the ACME Super ATM
First, we need to gain agreement on capabilities by
identifying all of the primary use cases for the ACME Super
ATM. In practical terms this means that we need to get everybody to
agree that a customer should be able to withdraw cash, deposit
funds, transfer funds, and all the things you would expect from a
conventional ATM, plus novel things like paying bills and purchasing
theater tickets. We won't worry about the structure of the model or
things like inclusion or extension, or generalization of either use
cases or actors. We simply want to make sure we really understand
all the major things the system will have to do. In addition, we
need to outline the basic flow and identify the alternative flows of
each use case so that we have a general understanding of its
scope. The next thing we need to do is to identify the
architecturally significant scenarios. For the ACME
Super ATM, many of the architecturally significant scenarios
arise not from the functionality of the ATM, which is fairly simple.
Rather, they arise from the alternative flows related to system
failure, security and recovery, and from the need to run a large
number of transactions in parallel on the ATM network. We document
these architectural scenarios in our Software Architecture
Document.
In order to assess the scalability of the proposed solution, we
are going to simulate running 1,000 simultaneous withdrawals of
cash. We also need to evaluate the security of the architecture of
the proposed solution by simulating physical tampering in an attempt
to rob the ATM. We will also truncate the network connection during
a cash withdrawal, and then cut power to the ATM in the middle of a
transaction, to test the fault tolerance and failure recovery
capabilities of the system. For example, if we indicate that we want
to withdraw a particular amount but lose power before the actual
money is dispensed, can the transaction be rolled back? Let's also
make sure that if we dispense the money but lose power before the
transaction is actually completed with the bank that it will be
completed once power is restored.
We should also do some work on configuring new kinds of
transactions to ensure that we will be able to do things other than
dispensing cash. To evaluate this, we could design, implement, and
test the scenario in which we print a theater ticket instead of
dispensing cash.
For each of these scenarios, we create a use-case realization,
which is basically a sequence or interaction diagram that
identifies the components we are going to use to fulfill the
behavior specified by the scenario so that we can allocate
functionality out to them. At the same time, we are going to develop
test cases that validate the scenarios so that we know what the
desired behavior is.
It's worth spending a moment considering what we mean by
testing in the Elaboration phase. In conventional thinking,
testing (usually performed in a later phase) primarily focuses on
validation: making sure the system behaves as specified. When we
test in the Elaboration phase, though, we are really trying to
uncover problem areas that we need to work on, rather than
validating that the behavior is correct. As a result, we want to
focus more on load testing, performance, and throughput, and not so
much on stability and low defect counts. In addition, we don't want
to spend any amount of time on testing the user interface at this
point, since that will change greatly over the remainder of the
project.
Managing Scope Changes in the Elaboration Phase
We typically end the Elaboration phase having identified more
work than we started the phase with. The reason for this is simple
-- we have now had some time exploring the requirements to find out
what is really needed to solve the problem, and this usually
means there is more work to do than we initially thought. From a
planning perspective, if the project was already tightly scheduled
or budgeted, this means that one of several things may need to
happen:
- Extend the schedule
- Extend (increase) the budget
- Extend both the schedule and the budget
- Scale back the scope of the solution
Extending the schedule, the budget, or both may be the right
thing to do. If the problem is valuable enough to solve, or perhaps
mandatory to solve, then asking for additional time or budget will
likely be met with little resistance, provided that the new
estimates are credible. The work we have done so far will help here:
since we now have built and tested the technically complex parts of
the solution, our certainty that we can build the solution has
increased significantly. In addition, building parts of the solution
also reduces the amount of work remaining (that we need to
estimate), further reducing the estimation error. The project going
forward is much easier to estimate than the part of the project that
is behind us.
Still, there may be reasons why we should cancel the project at
this point. It is obvious that if the proposed solution is
technically infeasible then we should not continue the project.
Sometimes this happens, but it is more likely that we find that the
solution is significantly more expensive than we had originally
hoped. The decision at that time is whether we should increase the
project funding and continue. We should base this decision on the
threshold for maximum project funding -- which was established back
in the Inception phase when we considered the value of solving the
problem -- and its close cousin the maximum amount we would be
willing to spend to solve the problem7.
If we find that the cost of solving the problem exceeds the
benefits of solving the problem, then the option that remains for us
is to reduce the scope of the solution. This typically involves some
fairly intense negotiation between the project manager and the
stakeholder representatives (people representing the groups affected
by either the problem or the solution) to determine what can be cut.
This negotiation process is typically iterative as well -- removing
requirements often has unexpected effects on the cost and schedule
estimate. In addition, when eliminating a particular requirement it
is often difficult to determine the cost effect without doing a fair
amount of investigative work, perhaps even building some small
prototypes to assist in the estimation.
Likely candidates for scope reduction are alternative use case
flows. You will rarely be able to eliminate entire use cases, but
you might determine that some of the alternative flows are not
needed or are so unlikely to occur that they need not be supported.
Many teams try to manage scope at a "feature"8
level, but the lack of a clear definition of what a feature is, as
well as the fact that a feature may cut across (and effectively
invalidate) use cases, makes them relatively useless for scope
management purposes.
Concluding the Elaboration Phase
At the end of the Elaboration phase we need to be rather
unyielding on the issue of mitigating technical risks -- if we
have mitigated them then we are ready to proceed to the
Construction phase. If we have not, however, we should not fool
ourselves into thinking that we are ready to move ahead. Remember,
once we reach the Construction phase we have gone down a path that
we cannot easily retrace without potentially throwing out lots of
work. The impact on schedule and cost of doing this is likely to be
severe, potentially putting the project at risk. We should not make
the decision to conclude Elaboration lightly.
Coming back to our ACME ATM example, let's see what this would
mean. At the end of the Elaboration phase we need to have a stable,
proven architecture that can deal with the technical risks we
identified earlier, as well as any new risks that we have discovered
during the Elaboration phase. This means that we have tested
scenarios in which we have tried to break into the system, caused
the network to fail, and disconnected the power, as well as running
our most likely transactions with thousands of simulated users. If
we have done all this successfully, then we should be feeling pretty
good about the viability of our project.
In addition, because we know a lot more about the solution we
ought to have much better confidence in our estimates by now. This
is not only because we have concrete information upon which we can
base estimates (such as function point counts), but also because we
have more information in the form of real code (which we can
start driving through a CoCoMo II model to cross-correlate our
function point-based estimate). Furthermore, we have identified all
the use cases -- which means that we are not going to discover any
major new things the system will need to do -- and we have the major
architectural scenarios detailed. We also have all the
architecturally significant supplementary specifications documented.
We should have completed test plans for these requirements and
scenarios, and we should have a partially completed design model,
test cases, and executable code. In short, we have a lot of the
important work out of the way. All this means that we have a very
stable basis for the remainder of the project.
Figure 13 shows our overall progress to date.
|
| Figure 13: Reviewing progress to date
|
Planning and Managing the
Construction Phase
The focus of the Construction phase is primarily on managing
the logistical details of getting the rest of the work done in the
time allotted. With the solution architecture in place following
the Elaboration phase, it is common to see the size of the project
team increase to allow more work to proceed in parallel9.
The rest of the work follows a pattern similar to that of the
Elaboration phase: the remaining scenarios are detailed, analyzed,
designed, implemented, and tested. In the Construction phase we have
to implement all functionality, including going back to
technically simple code that we stubbed-out in the Elaboration
phase. As we implement the rest of the functionality, we also need
to continue to run the architecturally oriented test cases from the
Elaboration phase to ensure that new work does not degrade or
destabilize the architecture.
The testing work changes character as we enter the Construction
phase. Up until this point we have focused on proving the
suitability (Inception) and technical feasibility (Elaboration) of
the solution. Our testing has reflected that -- we have not really
tested the user interface, although we have done extensive usability
design work to ensure that the visual style and metaphors used in
the application are stabilized. With this work behind us and the GUI
stabilizing, we can start GUI testing in earnest. To reduce the
ongoing cost of running these tests we will want to automate most of
the GUI tests so that we can run them after every build.
In addition to this development work, it is now time to start
writing documentation and support materials, and to start planning
the rollout of the solution; the actual rollout will occur in the
Transition phase, but the planning work needs to start now.
Managing Scope in the Construction Phase
In addition to the scope management strategies discussed above
(Elaboration), there are others that you can pursue if there appears
to be too much work left to do. One strategy that might reduce the
amount of work while not greatly increasing risk is to reduce the
formality of work associated with some of the simpler scenarios. In
practical terms this means that we can make a conscious choice to
merely outline (and not detail) simple scenarios that are already
well understood. It might also mean that we decide not to do formal
analysis and design using modeling techniques, but instead use rapid
prototyping tools to build these simpler system parts. Behavior that
is a good candidate for this strategy tends toward simple data
management:
- Add, modify, and delete
- Simple menus and navigation
- Behavior governed by simple business rules
Taking this approach enables us to conserve valuable time for
scenarios that implement complex business transactions in which
making the wrong decision would be very costly.
Strategies for Managing Change
It is common for the scope of the project to increase throughout
the Elaboration phase and into the Construction phase. This is not
necessarily bad -- it results naturally from understanding more
about the real problem being solved and the cost of potential
solutions. A problem arises because the schedule and budget for the
project do not typically expand in tandem with the scope. In
addition, if you do not properly manage expectations, they do not
adjust to the increase in scope. Therefore, many projects fail
because they take on the additional work without getting buy-in from
all the stakeholders. The result is a perception that the project
has failed (to meet budget and schedule, at any rate) even though
the project team thinks they have done the right thing.
This problem is both easier and harder to solve than it sounds.
The easy part of the answer is that solving the problem is a simple
matter of getting the stakeholders to agree on what is important,
including whether achieving the new scope warrants changes in budget
and schedule. The hard part is that this is not that easy --
projects typically have a diverse set of stakeholders that do not
necessarily share the same objectives.
A couple of things can make this easier. The first is
establishing at the outset an expectation of the fact that the scope
of the project is going to change, and that you are going to have to
work through the issues of scope, schedule, and budget. The second
thing that we need to do is to get all the stakeholders to agree on
a process for how decisions about these issues are going to be made.
Getting agreement on this early makes it easier to have the
discussion later on.
Concluding the Construction Phase
By the end of the phase, we will have implemented all the
functionality and will be ready to start rolling out the application
to its users. As discussed previously, this does not necessarily
mean that we ended up where we thought we would -- but if we have
been successful in managing risks and scope it means that we have
made the trade-offs necessary to deliver the right solution within
an acceptable time frame and budget.
If we have in fact met our goals of a "good enough" solution, it
is important that we know when to stop. It is tempting to throw in
"just one more feature", but we need to resist the temptation.
Adding things now will very likely delay the project and may
destabilize the delivery of the solution. Furthermore, keep in mind
that most systems are too complex and feature-packed to be really
useful. In many cases we would be better off reducing the number of
features, making the essential scenarios work very well, and
ensuring that the system is easy to use.
Planning and Managing the
Transition Phase
If we have done our job in the preceding phases, the Transition
phase is focused on delivering the solution to its intended users.
There is still some activity in each of the disciplines, however,
with most of the effort focused on deployment and fixing
defects. Moreover, while we should not plan to be implementing
new requirements at this point, there will inevitably be
requirements (small in scope if we have done a good job managing
them so far) that are discovered, analyzed, designed, implemented,
and tested. There will also, naturally, be defects to fix.
At this point, however, it's not always all about development.
Most significant systems have significant operational aspects that
we have been working to sustain throughout the project. Now is the
time to move the application from a development environment into a
production support environment. This means that we need to train
support staff, establish operating procedures, and convert
production data before the solution can be considered
complete.
Furthermore, very few systems are so intuitive to use that they
require no training. In fact, many of today's solutions involve not
only new software and hardware, but also changes to business
processes. During the earlier phases we should have planned,
designed, and tested these business process changes, and now it is
time to put them into place (along with the system changes) to
support the new business model. We will have drawn on our use cases
to develop appropriate training and documentation, and now we can
take advantage of that work.
The Transition Phase for the ACME Super ATM
In our ACME Super ATM example, the kinds of things that we would
need to do relate mostly to the logistics of getting the software
installed on the ATMs in the manufacturing operation, deploying
these machines out to the appropriate locations, and getting them
configured and running on the ATM network. The actual roll-out of
systems will continue over a period of years, and will represent a
whole program of its own, so our principal concern is on the first
wave of deployments to make sure that the ongoing deployment efforts
will be smooth.
Concluding the Transition Phase
As we have done at the end of each iteration and each phase, we
need to take time to evaluate our results in the Transition phase.
In addition, since we are at the end of the project, we also need to
take stock of the overall project. Even if the project has fallen
short of its goals, and maybe especially if it has fallen short, we
need to take time to understand what has gone well and what we need
to work on in future projects. It is natural to want to move on from
the project at this point, particularly if it has been a success.
Taking time now may help us later, and we need to make it a
priority.
Summary
In this article we have walked through each of the phases of a
project, focusing on their purpose in the broader project. We have
considered the risks addressed in each phase, and discussed
strategies for dealing with these risks. Throughout the project, we
have seen how use cases hold the project together by focusing our
attention on how the stakeholders are going to use the system.
We have also discussed how different estimation approaches help
us to plan and manage the project. In every phase we need to provide
estimates and manage resources and risks, although the work is
slightly different in each because each phase has a different risk
focus. We discussed how iteration and phase-end milestones are used
to evaluate progress and keep the project on track.
An iterative approach to developing solutions is a powerful tool
that helps us to bring predictability and responsiveness to solution
development efforts. Using these tools gives us an edge in
delivering the solutions that our stakeholders expect of us, in a
timely and cost effective manner.
Footnotes
1 A technique used to implement technically simple
parts of the system superficially by hard-coding a default response
to a function call. As an example, a function isValid(someObject)
could be stubbed-in by returning a 'true' value instead of actually
performing the validation. We would use this technique when the
implementation of the function will not affect the evolving
architecture of the system. By postponing implementation of this
function, we free ourselves to focus on more challenging aspects of
the system's architecture.
2 Adapted from Walker Royce, Software Project
Management: A Unified Framework, p. 276.
3 "Constructive Cost Model", see
http://sunset.usc.edu/research/COCOMOII/
4 This is one of the implicit tenets of approaches
like eXtreme Programming, in which the "user representative" is
fully responsible for communicating the business problems and
objectives-even much of the solution definition-leaving the
development team to focus purely on development issues. In practice,
we have found that it is important for the development team to
understand the business problem so that they can participate in
finding creative solutions. This approach has a price-technical
teams must become much more involved in understanding the business
in order to be successful, and they must consciously accept this new
responsibility.
5 One customer with whom we have worked created a
serious problem for themselves by locking in the schedule and
funding for projects before they even understood the problem or
potential solutions. Project managers' compensation was put at risk
if they did not meet the arbitrarily determined cost and schedule
targets: needless to say, nearly every project came in on time and
within budget. However, since the projects were created with very
little idea of what needed to be delivered, the deployed solution
often failed to produce meaningful business results. In this case,
the project funding and performance measurement model, instead of
improving results, was actually a strong contributing factor to poor
solution results.
6 Nothing is absolutely irrevocable, but what we mean
here is this: we are going to make decisions that, if reversed or
changed, are going to threaten the viability of the project. In
other words, we had better do our homework to make sure that these
decisions are correct.
7 The maximum amount we would be willing to pay to
solve a problem takes into account the required rate of return for
projects of a similar risk, and is essentially the net present value
of the benefits less the costs of solving the problem.
8 A feature really has no consistent definition; it is
basically some capability of interest to someone. The lack of clear
definition of what is and is not a feature is one of the reasons why
features are not very useful for scope management.
9 There is a famous observation (dubbed Brooks'
Law after Fred Brooks, who wrote about it in his seminal work
The Mythical Man-Month) that says that adding people to a
late project makes it later. This is true in cases where the
architecture is not stable and work cannot be effectively
partitioned into independent units that can be performed by
semi-independent teams. In these cases, the overhead of teams that
have to constantly communicate to avoid conflicting with one another
actually slows down the work of everyone, resulting in less work
getting done even though more people are working on the project.
About the author
 |
|
|
 |
Worldwide communities of practice architect Kurt Bittner
joined Rational Software ten years ago and has worked in the
software industry for more than twenty-one years. Improving
the effectiveness of software development organizations,
especially through software engineering management and process
change, has been his principal focus. A member of the original
IBM Rational Unified Process, or RUP, development team, he
later managed the RUP development organization as well as
other product development organizations inside IBM. In
addition to co-authoring Use Case Modeling
(Addison-Wesley, 2002), he has also contributed to several
other books and authored numerous
articles. |